Fortunately, the Developer was able to provide ground investigations data from both within the site and beyond into the highway. This included a ground penetration radar (GPR) survey and a manhole survey, both of which helped to position existing buried utilities to help strategically position trial holes and provide accurate sewer depth data. Additionally, following liaison with the Developer and following our desktop study into historical land use, it was already evident that encountering contaminated ground was very likely, therefore further contaminate testing wasn’t necessary and either ductile iron (DI) or ‘barrier’ polyethylene pipe would be necessary to complete the diversion.
Therefore, ground investigations would only be necessary to position buried utilities, identify a proposed route, understand required installation depths, and to collect ground samples for ground property analysis so that necessary concrete pipe anchoring and thrust could be effectively calculated.
Route Decision & Pipe Selection
Following ground investigations, managed by NPTEE and undertaken on site by Envolve Infrastructure Ltd, and further liaison with Bristol Water operational management, it was NPTEE’s duty to present the results and provide recommendations via a presentation to all project stakeholders. We highlighted findings from both site and desktop studies, whilst providing the subsequent advantages and disadvantages of both options, together with associated build cost estimations so that Bristol Water could make an informed decision.
Although slightly more expensive, Option 2 was selected, mainly due to a reduced risk to health and safety, the environment and future operation and maintenance.
Pipe size and material selection was based on size requirement, pressure rating need, availability, cost, ease of use on site, ground contamination risk, installation depth and sustainability. Following liaison with both the Client for size requirements and pipe suppliers, it was decided to use both 400mm diameter ductile iron (DI) pipe for the end connections, with 450mm diameter ‘barrier’ polyethylene (PE) pipe between and for the majority of the necessary length.
The DI connections would ensure strength and ease any future removal/replacement of fittings. The PE pipe would reduce cost and weight, easing on-site operations, and would be easier/more efficient to install. Additionally, the adoption of PE pipe would prove to be more sustainable and reduce cost further due to butt fusion jointing replacing the need for mechanical fittings and reducing the risk of joint failure that leads to customer supply interruptions, a key OFFWAT directive.
We therefore pressed on with the Detailed Design phase.
Detailed Design
Once the route had been decided, with buried utility locations confirmed, proposed development plans understood and following the receipt of ground sampling results, technical design could be undertaken.
There were two clear and fundamental problems that still needed to be resolved:
- Available space for sufficient concrete anchoring and thrust pipeline support whilst maintaining highway, residential and business access, especially where the end connections were being undertaken.
- The maintenance of customer supply and minimisation of water supply interruptions to the supply network, including the sequencing of key construction activities.
With a 400mm diameter ductile iron pipe being exposed to a working pressure of approximately 9 Bar, a significant amount of concrete would be necessary to ensure that the main remains stable. In addition, in accordance with CIRIA guidance, a surge factor of 5 Bar needed to be applied (x1.5 working pressure), therefore meaning that any concrete anchoring or thrust would need to support a pressure of 14 Bar.
When analysing the ground test results, the soil was classed as soft-firm clay based on Atterberg testing. The moisture content (NMC) was found to be greater than the Plastic Limit (PL) and the undrained shear strength was conservatively assessed to be 40 kPa. Similarly, a conservative assessment of the thrust reduction factor was calculated, with a value of no less than 3 being adopted.