Former Brunel Ford Site, Muller Road, Horfield

15”AC Trunk Water Supply Main Diversion.

To support the development of new social housing on a brownfield site in Horfield, Bristol, NPT Engineering & Environmental Ltd (NPTEE) were commissioned by Bristol Water’s Development Services team to undertake the role of Designer in accordance with HSE 2015, providing full pre-construction design and environmental management/support for the diversion of an existing 400mm diameter asbestos cement (AC) water main.

Figure 1: Proposed development layout (blue highlights existing trunk water main position)

Unfortunately, approximately 120m of this existing and strategically important 400mm diameter supply trunk main passed in an Easterly direction from the B4469 Muller Road, directly beneath and through the site causing significant difficulties with the approved design of the proposed development (see Figure 1 for development layout). Together with the required ongoing maintenance and safe operational access for Bristol Water, the positioning of necessary housing was proving to be very problematic when trying to maintain the existing position of this water main.

Therefore, to maintain supply to approximately 10,000 Bristol Water customers whilst appeasing the design of the approved development to maximise much needed social housing in the area, the decision was made to divert the water main, with the developer requisitioning Bristol Water to position it safely, maximising the site’s potential.

With the water main being so strategically important for the supply of water in both the local area and throughout the Bristol Water network, together with having a working pressure of approximately 8.5 bar (85.65m head), being constructed using asbestos cement, and being partially positioned beneath an extremely sensitive highway in a busy area, this wasn’t going to be a straightforward task!

Initially, the best route for the diversion needed to be decided, with two feasible route options being considered so that the main could be diverted from the B4469 Muller Road to a proposed connection point on the Eastern boundary of the development site. The first option routed the diversion via an existing public footpath and along the Southern perimeter of the site, with the second option diverting the new water main Northwards and further along Muller Road, entering the site via the existing and proposed site access and following the proposed site access road to reach the proposed reconnection point on the Eastern boundary of the site. As with most projects, both options had associated advantages and disadvantages, it was a case of deciding which was most advantageous with both current and future operation in mind.

 

Pipeline Route

Route Option 1

Click to enlarge image
Figure 2: Route option 1 following existing footpath (highlighted in red)

Highlighted as the preferred route by the Developer during the early stages of planning, this route avoided the development site for the most part, only needing to enter the site partially for reconnection (see Figure 2). This option also had the shortest linear distance, therefore would prove financially viable with regard to pipe/fittings required and construction time, causing little impact to the Developer’s construction programme. However, although the advantages were clear, NPTEE needed to consider the build with safety, ‘buildability’, future operation/maintenance, and the environment in mind, with a number of significant concerns highlighted.

Click to enlarge image
Figure 3: Public footpath from Muller Road along Southern perimeter of site with established trees and retained ground

This route, along the Southern boundary of the site, was adjacent to a retaining brick wall that acted as a boundary with land belonging to a supermarket that was built upon land at a significantly lower topographic level (see Figure 3). The associated drop in ground level was approximately 2.5m and the working width available between the site and the retaining wall for pipeline installation would have been approximately 3-4m. In addition, a number of fully grown trees were positioned along the route in the narrow grassed verge positioned adjacent to the footpath. These trees become an immediate concern. They were probably helping with ground stabilisation, with root systems not only supporting the ground but also removing water from behind the retaining wall, but additionally, they presented an ecological risk, possibly  supporting wildlife and helping biodiversity in the area.

From a construction perspective, even with the trees being removed, the working width would be narrow, significantly reducing safe working space and space for the installation of suitably sized concrete pipe anchoring and thrust,. In addition, removal of the trees would likely destabilise the ground, leading to possible failure of the retaining wall and significant risks  to the operational team and users/staff of the adjacent Supermarket. Together with these hazards and associated risks in mind, time consuming and expensive mitigation would be necessary to further stabilise the ground. However, mitigation would only reduce risk, not eliminate it. Construction time would inevitably increase, and necessary mitigation would be expensive, leading to significantly higher costs. This would, therefore, reduce the assumed saving that was previously highlighted as an advantage whilst impacting biodiversity by removing an established tree line and habitat rich boundary between the site and the Supermarket.

Route Option 2

This option (see Figure 4) required close liaison with the Developer and highways. It had a longer linear length with the need to break significantly more ground in a busy/sensitive highway and the avoidance of a number of buried utilities including high voltage electric, both low and medium pressure gas mains, fibre optic/telephone ducts, and both storm and foul water sewers.

Click to enlarge image
Figure 4: Route option 2 (highlighted in red) follows Muller Road and enters site via the proposed development access

At first glance, this option would seem more disruptive to both the site and the public. It also seemed more expensive whilst presenting increased risk from buried utility hazards. However, there was less risk of ground destabilisation, therefore no need for ground stabilisation works and the risk of contact with existing buried utilities could be effectively managed with further and appropriate pre-construction investigations. Additionally, there would be no impact to existing environmental habitats and biodiversity, requiring no environmental reinstatement/re-establishment, and the future operation and maintenance of the water main would be significantly easier and safer.

As with ‘Route Option 1’, ground investigation was necessary to evaluate existing utility positions, ground strength and ground contamination. However, this option posed greater risk to existing buried utilities and would no doubt increasingly impact the highway. However, these hazards could be managed if located strategically, with little difference to overall cost.

Fortunately, the Developer was able to provide ground investigations data from both within the site and beyond into the highway. This included a ground penetration radar (GPR) survey and a manhole survey, both of which helped to position existing buried utilities to help strategically position trial holes and provide accurate sewer depth data. Additionally, following liaison with the Developer and following our desktop study into historical land use, it was already evident that encountering contaminated ground was very likely, therefore further contaminate testing wasn’t necessary and either ductile iron (DI) or ‘barrier’ polyethylene pipe would be necessary to complete the diversion.

Therefore, ground investigations would only be necessary to position buried utilities, identify a proposed route, understand required installation depths, and to collect ground samples for ground property analysis so that necessary concrete pipe anchoring and thrust could be effectively calculated.

Route Decision & Pipe Selection

Following ground investigations, managed by NPTEE and undertaken on site by Envolve Infrastructure Ltd, and further liaison with Bristol Water operational management, it was NPTEE’s duty to present the results and provide recommendations via a presentation to all project stakeholders. We highlighted findings from both site and desktop studies, whilst providing the subsequent advantages and disadvantages of both options, together with associated build cost estimations so that Bristol Water could make an informed decision.

Although slightly more expensive, Option 2 was selected, mainly due to a reduced risk to health and safety, the environment and future operation and maintenance.

Pipe size and material selection was based on size requirement, pressure rating need, availability, cost, ease of use on site, ground contamination risk, installation depth and sustainability. Following liaison with both the Client for size requirements and pipe suppliers, it was decided to use both 400mm diameter ductile iron (DI) pipe for the end connections, with 450mm diameter ‘barrier’ polyethylene (PE) pipe between and for the majority of the necessary length.

The DI connections would ensure strength and ease any future removal/replacement of fittings. The PE pipe would reduce cost and weight, easing on-site operations, and would be easier/more efficient to install. Additionally, the adoption of PE pipe would prove to be more sustainable and reduce cost further due to butt fusion jointing replacing the need for mechanical fittings and reducing the risk of joint failure that leads to customer supply interruptions, a key OFFWAT directive.

We therefore pressed on with the Detailed Design phase.

Detailed Design

Once the route had been decided, with buried utility locations confirmed, proposed development plans understood and following the receipt of ground sampling results, technical design could be undertaken.

There were two clear and fundamental problems that still needed to be resolved:

  • Available space for sufficient concrete anchoring and thrust pipeline support whilst maintaining highway, residential and business access, especially where the end connections were being undertaken.
  • The maintenance of customer supply and minimisation of water supply interruptions to the supply network, including the sequencing of key construction activities.

 

With a 400mm diameter ductile iron pipe being exposed to a working pressure of approximately 9 Bar, a significant amount of concrete would be necessary to ensure that the main remains stable. In addition, in accordance with CIRIA guidance, a surge factor of 5 Bar needed to be applied (x1.5 working pressure), therefore meaning that any concrete anchoring or thrust would need to support a pressure of 14 Bar.

When analysing the ground test results, the soil was classed as soft-firm clay based on Atterberg testing. The moisture content (NMC) was found to be greater than the Plastic Limit (PL) and the undrained shear strength was conservatively assessed to be 40 kPa. Similarly, a conservative assessment of the thrust reduction factor was calculated, with a value of no less than 3 being adopted.

Click to enlarge image
Figure 5: End Connection Detail 1 (Enabling Point 1/Anchor Block 1 (AB1) with support slab) - Plan View (red dashed line highlights new install)

Being installed with a cover depth of approximately 1.1m to pipe crown and needing to withstand horizontal forces of approximately 170 kN, substantial concrete anchoring would be necessary at each end connection. Therefore, with limited space and depth at both locations, design of each anchor block would require a bespoke approach.

It was decided to incorporate both fibre reinforced concrete with appropriately sized steel reinforced shear keys to significantly reduce the size of the anchor blocks (see Figures 5, 6, 7 & 8).

This would not only allow each block to be cast with greater ease in the space available, but would also reduce concrete use, therefore reducing build cost and improving sustainability.

Figure 6: End Connection Detail 2 (Enabling Point 2/Anchor Block 2 (AB2) with support slab) - Plan View (red dashed line highlights new install)
Figure 7: End Connection Anchor Block Details
Click to enlarge image
Figure 8: Shear key design with steel reinforcement

Construction Stage Sequencing

With regard to the maintenance of water supply to the network and minimising interruptions NPTEE provided a sequencing plan for the Contractor to follow (see Figures 10, 11 & 12) and adopted ‘Enabling Points’ at each end connection. These Enabling Points were to be installed as an initial action and prior to the installation of the new diversion pipework. They would require only one shut if necessary to install new pipe branches with a number of control fittings. This would allow the safe control of water supply on site, maintaining supply via the existing water main while the new diversion was being installed. It would also allow the safe and swift transfer of supply to the new diversion whilst ensuring the safe decommissioning of the abandoned section without interrupting supply.

Following liaison with the Contractor, simple to understand construction sequencing was provided with various stages highlighted (see Figures 9, 10 & 11).

On full completion of detailed design and subsequent liaison/approval with both the Principal Contractor (Envolve Infrastructure Ltd) and the Client (Bristol Water) throughout the design stage, NPTEE coordinated a final on-site meeting and our Detailed Design Review (DDR), confirming current design and highlighting both health & safety and environmental hazards, mitigation undertaken and further mitigation requirements needing to be undertaken by the Contractor to ensure full awareness and agreement with all stakeholders.

Click to enlarge image
Figure 9: Sequencing of Works Stage 1 - Installation of End Enabling Points (AB1 & AB2) (red highlights new install)
Click to enlarge image
Figure 10: Sequencing of Works Stage 2 - Installation of new 450 PE water main diversion (red highlights new install)
Click to enlarge image
Figure 11: Commissioning of new 450 PE diversion & Abandonment of 15”AC water main section (green highlights abandoned water main section)

Following written agreement, NPTEE delivered all construction drawings together with the Designer’s Preconstruction Information pack, including all utility returns, health & safety documentation, the environmental Construction Environmental Management Plan (CEMP) and any relevant guidance documents. This information was then used to price and organise the necessary construction phase of the project, together with organising necessary requirements with 3rd parties such as the local highways team.

NPTEE’s design delivery ensures an effective and buildable design whilst protecting the environment, avoiding confusion, reducing costs where feasible to do so and maintaining positive relationships by considering and welcoming input from all parties involved.

NPTEE don’t leave it there! We also ensure assistance throughout construction, providing ongoing advice if required and the completion of any further technical deliveries if design changes are found to be necessary when on site.