Gaol Ferry Wall Renovation, Bedminster, Bristol

Environmental Impact Assessment (EIA) screening opinion

Alun Griffiths (Contractors) Ltd were appointed by Bristol City Council to repair ‘Asset NCN16’ – a stone masonry wall located along the river bank and within the River Avon New Cut in Bristol (BS3 1AS).

The asset is approximately 80m long and 6.1m high and had suffered significant loss of masonry blockwork where much of the subsequent debris is visible at the wall’s toe having previously collapsed into the watercourse.

The asset had been singled out as a priority repair for Bristol City Council due to its prominence within the River Avon New Cut and the scale of the failure. The asset is thought to have been constructed as a facing wall built to protect the bedrock behind the scour. The works propose to repair and stabilise ‘Asset NCN16’ so it can withstand erosion from the River Avon.

Figure 1: Location Plan (image courtesy of Google Maps)

NPT Engineering & Environmental Ltd were appointed by Alun Griffiths (Contractors) Ltd to complete an Environmental Impact Assessment (EIA) screening opinion for submission to BCC for determination to confirm whether the planned works were an EIA development. This included highlighting all the key environmental constraints across the site together with any appropriate mitigation that may be necessary to ensure that the works remain compliant with The Town and Country Planning (Environmental Impact Assessment) Regulations 2017.

In this instance, the Preliminary Ecological Appraisal (PEA), completed from a boat upon the river, searched for signs that could confirm the presence of otters and beavers, including otter feeding remains, spraints, prints, tracks, lay-ups and holts, beaver food caches, scent-mounds, slides and burrows. Considering the tidal nature of the river, field signs below high tide could be washed away during each tidal cycle.

The survey took place on a flooding tide to maximise the chance of recent field signs remaining for the duration of the survey period. At the time of the survey no evidence of beaver was recorded during the survey period. Multiple otter prints were identified in the fresh mud heading upstream of the site, confirming use by commuting otter within several areas of bankside habitat which were deemed suitable for resting otters. Remote cameras were then used to monitor these features for a period of six weeks and checked over by the ecologist.

Figure 2: Wall fascia collapse into the River Avon

All this information plus further details from the PEA survey and characteristics on Invasive Species, Designated Sites, Trees and Hedgerows, Landscape, Archaeology and Cultural Heritage, Nuisance, Soil Contamination, Public Rights of Way, Waste Management, Traffic, Flood Risk Assessment, Flood Risk Activity Permit, Marine Licence, Common Land and Pollution Prevention during Construction was detailed in the EIA screening opinion which was submitted to BCC during November 2024. It was confirmed that the planned works were not deemed an EIA development in January 2025.

Prior to the works starting on site, NPT issued a Construction Environmental Management Plan (CEMP) to Alun Griffiths Ltd summarising the key environmental constraints across the site together with appropriate mitigation and recommendations on how these can be managed during construction.

NPT Engineering & Environmental Ltd were able to offer on-site environmental consultation advice and support to Alun Griffiths (Contractors) Ltd to ensure the environment remained a key consideration during construction.