Miskin Scout Hall, Miskin, Pontyclun – Environmental support for a sewer replacement

Miskin Scout Hall, Miskin, Pontyclun – Environmental support

Services provided by NPT Engineering & Environmental Ltd:

• Environmental Management (2024);
• Preliminary Ecological Appraisal (PEA)
• Tree Preservation Order (TPO) Application
• Flood Risk Activity Permit (FRAP) Application
• Construction Environmental Management Plan (CEMP)
• Ongoing advisory support during construction

Figure 1: Location Plan (image courtesy of Google Maps)

Envolve Infrastructure Ltd appointed NPT Engineering & Environmental Ltd to assist with a sewer replacement that they were undertaking on behalf of Dŵr Cymru Welsh Water (DCWW) at Miskin Scout Hall in Pontyclun, parallel with the River Ely.

Due to cumulative and catastrophic failures of an existing sewer pipeline currently passing through the Miskin Mill campsite, rendering it unusable, inoperable and presenting a significant contamination risk, a sewer length of approximately 240m required replacement.

To assist with facilitating the planned works, NPT Engineering & Environmental Ltd initially completed a Preliminary Ecological Appraisal (PEA) to identify the existing on-site habitats and any noticeable protected species that may be present. The PEA also provided recommendations on how to manage such constraints during construction.

Click to enlarge image
Figure 2: Route for sewer replacement with surrounding and well established trees

Trees surround the proposed construction area, a number of which are protected by Rhondda Cynon Taff County Borough Council (RCTCBC) Tree Preservation Order (TPO 6, 1976). To facilitate safe construction, the removal of 3 No. trees (2 No. TPOs) was necessary, together with some limb removal and crown reduction within the root protection zone (RPZ) of the protected trees.

An Arboricultural Impact Assessment (AIA) and Arboricultural Method Statement (AMS) were completed and issued together with the TPO application, all of which was submitted to RCTCBC in May 2024 and subsequently granted in June 2024, within their statutory 6-week determination period.

Construction also needed to take place within Flood Zones 2 & 3 of the River Ely and within 8m of the watercourse. This therefore required a Flood Risk Activity Permit (FRAP) application to be completed and submitted to Natural Resources Wales (NRW) to ensure that the works remained compliant. The FRAP application summarised information from the PEA survey and included an Environmental Risk Assessment with a supporting statement and associated design plans. Once collated, the application was submitted to NRW in May 2024 and subsequently granted in August 2024.

Click to enlarge image
Figure 3: Monkshood (Aconitum anglicum) (free image courtesy of Pixabay - image by Pascal Bondis

Initially, NRW expressed concern due to planned construction taking place within 100m of the Ely Valley Site of Special Scientific Interest (SSSI), designated for its population of monkshood (Aconitum anglicum). They therefore requested assurance that the construction would not inadvertently cause a further spread of this plant. A further survey for the presence of monkshood was completed by an ecologist in July 2024, focusing on the likely working areas on site, areas adjacent to these likely working areas, and the riverbank. Fortunately, no Monkshood was found in any of these areas. The species would have been readily visible at the time of year that the survey took place, therefore it was reasonable to conclude that it was not present.

The proposed works were summarised within a Construction Environmental Management Plan (CEMP) which provided recommendations on managing all items mentioned above. This information was also briefed to the site construction team during the pre-construction meeting and therefore in advance of any construction activities taking place on site.

In addition, NPT Engineering & Environmental Ltd provided ongoing advisory support during construction, helping to ensure full compliance throughout all stages of the project.